13 Approval Process //

Following the finalisation of the TYNDP 2026 Scenario Report, the next steps are structured in line with the regulatory and governance framework set out under the TEN‑E Regulation. The publication of the joint Scenario Report by ENTSO‑E and ENTSOG marks the completion of the scenario-building phase, subject to approval. Once approved by the relevant governance bodies, the report is published and made available to stakeholders.

Within three months of receipt of the draft joint Scenario Report, ACER shall submit its opinion on compliance of the scenarios with the framework guidelines including possible recommendations for amendments.

Within three months of receipt of the opinion the Commission shall approve the draft joint Scenario Report or request the ENTSO for Electricity and the ENTSO for Gas to amend it.

Within two weeks of the approval of the joint Scenario Report the ENTSO’s shall publish it on their websites.